Pre-Construction Information: What Clients Must Provide Under CDM 2015

Pre-Construction Information: What Clients Must Provide Under CDM 2015

Pre-construction information is the information about the site, the existing building and the project that designers and contractors need to plan the work safely. Under CDM 2015, the client must provide it, as soon as practicable, to every designer and contractor appointed or being considered. It is one of the client's core duties, and it is one of the most often done badly.

Poor pre-construction information is rarely a safety failure on day one. It shows up later: an unexpected service in the ground, asbestos found halfway through a strip out, a structural surprise in an old building. Each one costs time and money, and some put people at risk.

What should pre-construction information include?

It should cover what a competent designer or contractor would need to know that they could not reasonably find out for themselves. HSE guidance lists the areas it should address, and in practice most packs include:

  • A description of the project, its programme and key dates
  • The client's management arrangements and any site rules
  • Existing drawings and structural information
  • Asbestos surveys, including a refurbishment and demolition survey where work will disturb the fabric
  • Information on existing services, above and below ground
  • Ground conditions, contamination and any site investigation reports
  • Existing health and safety files from earlier work on the building
  • Hazards specific to the site, such as occupied areas, restricted access, adjacent railways or public spaces

Where does the information come from?

Some of it the client already holds: drawings, previous health and safety files, surveys commissioned years ago. Some has to be commissioned: an up to date asbestos survey, a utility survey, a structural or ground investigation. Part of the principal designer's role under CDM is to help the client gather and provide it, but the duty to provide it sits with the client.

The common mistake is to hand over whatever is in the filing cabinet and call it complete. A ten year old asbestos management survey is not suitable for a refurbishment that will open up walls and ceilings. Drawings of an old building may not show what was actually built. Information should be checked for gaps, and the gaps filled before designers and contractors rely on it.

InformationCommon gapWhat fills it
AsbestosOnly a management survey existsRefurbishment and demolition survey for the areas affected
Buried servicesStatutory records onlyA utility survey with trial holes where needed
StructureOriginal drawings, unverifiedIntrusive investigation at key locations
GroundNo site investigationDesk study, then intrusive investigation

When should it be provided?

As early as possible. Designers need it to design out risk, which is much easier before the design is fixed. Contractors need it to price and plan the work properly. Information that arrives after the contract is let tends to become a change, and changes cost more than information.

It should also be kept up to date. If new information comes to light during the project, it needs to reach everyone who needs it.

What about notifiable projects?

A project is notifiable to HSE if the construction work will last longer than 30 working days and have more than 20 workers on site at the same time, or will exceed 500 person days. The client must submit the notification, known as an F10, before construction starts. Notification does not change the duty to provide pre-construction information, which applies to every project, notifiable or not.

How can a client get this right?

Start gathering information at feasibility stage, not at tender. Ask your principal designer to review what you have and list what is missing. Commission the surveys early enough that their findings can shape the design. And treat the pack as a living document rather than a one-off issue.

Our CDM advisor and health and safety team helps clients assemble pre-construction information, identify the gaps and meet their wider CDM duties. Spring & Co holds NEBOSH-qualified staff and CHAS accreditation, and has supported clients on CDM since the regulations were first introduced. Get in touch if you would like a review of what you have.