Since 1 October 2023, building work in England with more than one contractor needs a principal designer under the Building Regulations, whose job is to plan, manage and monitor the design so that the building complies with the regulations. This sits alongside the principal designer under CDM 2015, whose job is health and safety. Same title, different duties. One firm can hold both, but only if it is competent in both.

The new role came in through the Building Safety Act 2022, which added dutyholder duties to the Building Regulations. The aim was to make someone clearly responsible for compliance during design, rather than leaving it to be caught at inspection.

How do the two principal designer roles differ?

CDM 2015 principal designerBuilding Regulations principal designer
FocusHealth and safety risks during construction, use and maintenanceCompliance of the design with the Building Regulations
Legal basisConstruction (Design and Management) Regulations 2015Building Regulations, as amended from 2023
Main tasksPre-construction phase coordination, design risk, the health and safety filePlanning, managing and monitoring design work for compliance, coordinating designers
Appointed byThe clientThe client

What does the Building Regulations principal designer actually do?

In practice, the role involves:

  • Planning how design work will be carried out so it complies with the regulations
  • Coordinating the designers so their work fits together and compliance is not lost between disciplines
  • Checking that designers are competent for what they are doing
  • Liaising with the principal contractor on design work during construction
  • Helping the client meet its own duties, including information at completion

It is a management role. The principal designer does not personally check every calculation, but must have arrangements in place that make compliance the likely outcome and give evidence that it was managed.

Who can do it?

A person or organisation with the skills, knowledge, experience and behaviours to carry it out, and, for an organisation, the organisational capability. On many projects the lead designer, often the architect, takes the role. On complex or higher-risk buildings, clients sometimes appoint a specialist.

What matters is that the appointment is made deliberately and in writing, and that the client has checked competence. Appointing the architect by default, without discussing the role and fee, is a common gap.

What happens if the client does not appoint one?

If the client fails to appoint a principal designer where one is required, the client takes on the duties itself. Most clients are not equipped to carry them out. On higher-risk buildings, failure to meet dutyholder duties can also cause problems at the Building Safety Regulator gateways.

Does this apply to small projects?

The requirement to appoint applies where more than one contractor is involved, which covers most commercial projects. Domestic clients have their duties passed to others in some situations, much as they do under CDM. Either way, the purpose is the same: someone with the right knowledge is responsible for compliance during design.

What should clients do now?

  • Check whether your project needs a Building Regulations principal designer
  • Decide who will hold it, and whether the same firm will also hold the CDM role
  • Put both appointments in writing, with scope and fee
  • Check competence and keep a record of how you did

Our CDM advisor and health and safety team advises clients on both principal designer roles and supports them in meeting their own dutyholder duties, while our project management team builds the appointments into the project from the start. Talk to Spring & Co about your next project.