The Building Safety Act: What Has Changed for Clients

The Building Safety Act: What Has Changed for Clients

The Building Safety Act 2022 changed how building work is managed in England. Since 1 October 2023, every project carries dutyholder duties under the Building Regulations, similar in shape to CDM, and higher-risk residential buildings must pass through Building Safety Regulator gateways before construction starts and before anyone moves in. For clients, the practical change is that you now carry clear legal duties for compliance, not only for safety.

Many clients assume the Act only matters for tall residential towers. The gateway regime does apply mainly to those, but the dutyholder duties apply to building work of every size.

What are the new dutyholder duties?

The Building Regulations now name dutyholders, and the list will look familiar to anyone who knows CDM 2015: the client, the principal designer, the principal contractor, designers and contractors. Each has duties to plan, manage and monitor the work so that it complies with the Building Regulations.

For the client, the main duties are to make suitable arrangements for the work to comply, to allow enough time and resource for that, to appoint a principal designer and principal contractor where there is more than one contractor, and to check that the people appointed are competent.

It is worth stressing that the Building Regulations principal designer is a separate appointment from the CDM principal designer. One firm can hold both roles if it is competent in both, but they cover different things: CDM is about health and safety, the Building Regulations role is about compliance with the regulations.

What counts as a higher-risk building?

For the design and construction regime, a higher-risk building is one that is at least 18 metres high or has at least seven storeys, and contains at least two residential units. Care homes and hospitals meeting the height threshold are also included during construction.

These buildings no longer go through local authority building control. The Building Safety Regulator is the building control authority, and work passes through gateways.

GatewayWhenWhat it means
Gateway onePlanning applicationA fire statement is submitted with the planning application
Gateway twoBefore building work startsThe Regulator must approve the building control application before work can begin
Gateway threeBefore occupationA completion certificate must be issued before the building can be occupied

Gateway two is where many programmes have come unstuck. The Regulator expects a detailed, coordinated design at application stage, and significant changes afterwards need their own approval. Clients who are used to finishing the design while building have had to change how they plan.

What is the golden thread?

For higher-risk buildings, the golden thread is the accurate, up to date information about the building that must be kept from design through construction and into occupation. It is held digitally and handed over to the person responsible for the building once it is occupied. In practice it means keeping design decisions, changes and product information properly recorded as you go, rather than assembling them at the end.

What does this mean for a typical project?

If your project is not a higher-risk building, the day to day change is mostly about roles and records. You still use building control as before, but you need to appoint the right dutyholders, check their competence, and be able to show that compliance was planned and managed. A client who treats compliance as the contractor's problem alone is now exposed.

If your project is a higher-risk building, the change is bigger. Allow for the Regulator's approval time before work starts, get the design properly developed before the gateway two application, and plan change control carefully, because changes during construction need approval too.

Where should a client start?

With three questions. Is the building higher-risk? Who are the dutyholders, and are they competent? And who is keeping the records that show compliance was managed? If you cannot answer all three with confidence, get advice early. Our CDM advisor and health and safety team supports clients on the dutyholder roles under both regimes, and our project management service builds the approval stages into the programme from the outset.