The Construction Phase Plan: What Should Be in It

The Construction Phase Plan: What Should Be in It

A construction phase plan sets out how health and safety will be managed during the construction work. CDM 2015 requires one for every project, and the client must make sure it is drawn up before the construction phase begins. The principal contractor prepares it, or the contractor where there is only one. A good plan is specific to the site and the work, and short enough that people actually use it.

Construction phase plans have a reputation for being thick, generic documents that sit on a shelf. That misses the point. The plan exists so that everyone on site knows the arrangements, the rules and the particular risks of this job.

What should a construction phase plan contain?

HSE guidance sets out the areas it should cover. In practice a useful plan includes:

SectionWhat it covers
Project descriptionThe work, key dates, the project team and their contact details
Management arrangementsWho is responsible for what, supervision, communication and cooperation
Site rulesInduction, permits, access, PPE, restricted areas
WelfareToilets, washing, drinking water, rest and changing facilities
Specific risksHow the significant risks of this project will be controlled
Emergency arrangementsFire, first aid, evacuation, incident reporting

The specific risks section is where the value lies. Working at height, excavations, lifting operations, asbestos, work near live services, temporary works, occupied buildings and interfaces with the public all need project-specific arrangements, not a paragraph copied from the last job.

What does the client have to do?

The client must make sure a construction phase plan is drawn up before the construction phase starts, and that suitable welfare facilities are provided from the start of the work. The client does not write the plan, but it cannot simply assume it exists. A sensible client, or their CDM advisor, asks to see it and checks that it reflects the project.

The client also has a role in the information that feeds it. A plan can only address the risks the contractor knows about, which is why pre-construction information matters so much.

Is it a one-off document?

No. The plan should be reviewed and updated as the work progresses, particularly when new phases start, new contractors arrive or conditions change. A plan written for groundworks will not cover the risks of fit out in an occupied building. Regular review keeps it relevant.

What makes a plan good rather than just compliant?

  • It is specific to the site and work, not generic
  • It is proportionate: a small job needs a short plan
  • It is used in inductions and briefings, not just filed
  • It is updated when the job changes
  • It links to method statements and risk assessments for high-risk activities

How we help

Our construction health and safety team reviews construction phase plans for clients and helps contractors prepare plans that work on site, and our CDM advisors support clients in meeting their wider duties. Spring & Co is CHAS accredited and holds NEBOSH-qualified staff. Talk to us before your next project starts on site.