A good monthly cost report answers three questions on its first page: what is the project now forecast to cost, how has that changed since last month, and why. Everything else in the report supports those answers. If you finish reading your cost report and still cannot say whether the project is on budget, the report is not doing its job.
Cost reports are one of the main ways a client stays in control of a live project. They are also one of the most frequently skimmed documents on a job, usually because they are long, full of tables and hard to read quickly.
What should be on the first page?
A summary a busy client can read in two minutes:
- The approved budget
- The current contract sum
- The forecast final cost, including known changes and risks
- The movement since the last report, in pounds, with a short explanation
- The remaining contingency or risk allowance
- Any decisions the client needs to make, and by when
The forecast final cost is the number that matters most. The contract sum tells you what was agreed. The forecast tells you what the project is actually heading towards.
What sits behind the summary?
| Section | What it shows |
|---|---|
| Change register | Every instruction or variation, its status and its agreed or estimated cost |
| Risk register | Known risks that could cost money, each with an estimated value |
| Provisional sums | Allowances in the contract, and how they are being spent |
| Contingency drawdown | What has been used, on what, and what remains |
| Cash flow | Actual payments against the forecast, for funding and budgeting |
The change register is where most cost movement lives. Each change should show whether it is instructed, agreed or still being priced. Estimates for unagreed changes should be realistic, not the contractor's opening figure and not a hopeful guess.
Why include risks as well as changes?
Because a forecast that only counts agreed changes will always look better than the truth. If the team knows that ground conditions under part of the site are uncertain, or that a design element has not been fully coordinated, those risks have a likely cost. Putting a value against them, and showing it against the remaining contingency, gives the client an honest picture before the money is spent.
It also helps the conversation. A client who can see that three open risks could use most of the contingency will make different decisions about optional changes than one who only sees a healthy looking contingency figure.
How often should the numbers move?
Movement is normal. What matters is that it is explained. Each month the report should say why the forecast changed: a new instruction, a change agreed for less than estimated, a risk that went away, a provisional sum that came in over. If the forecast jumps without explanation, or stays exactly the same for months on a busy project, ask questions.
What makes a report easy to act on?
- Plain language. Descriptions a client understands, not only contract clause references.
- Consistent format. The same layout every month, so changes stand out.
- Clear decisions. If the client needs to approve something, the report says so and gives the deadline.
- Honest forecasts. Bad news reported early is far more useful than bad news reported late.
Who should produce it?
Usually the client's quantity surveyor or cost manager, working from the contractor's information but independently of it. The value of the report comes from that independence: the client gets a view of cost that has been checked, not simply passed on.
Our cost management and quantity surveying team produces monthly cost reports for developers, funders and public sector clients, and our project monitoring service reviews cost reporting on behalf of lenders. If your current reports leave you unsure where the project stands, talk to Spring & Co and we will show you what a clear one looks like.