A fair tender analysis compares bids on a like for like basis. That means checking each one for arithmetical errors, missing items, exclusions, qualifications and unrealistic rates, adjusting for them, and only then comparing prices. The lowest headline figure often stops being the lowest once those adjustments are made.
Tender returns rarely line up neatly. Contractors price the same documents in different ways, make different assumptions and add their own conditions. Without careful analysis, a client can choose a bid that looks cheapest and turns out to be the most expensive by the final account.
What does a tender analysis check?
| Check | Why it matters |
|---|---|
| Arithmetic | Errors in extensions and totals, which the tender rules say how to deal with |
| Completeness | Items left unpriced or included elsewhere |
| Exclusions | Work the contractor has said it has not priced |
| Qualifications | Conditions that change the risk the client carries |
| Rates | Unusually low or high rates, which can signal errors or loading |
| Preliminaries | Site set-up, management and time related costs against the programme |
| Programme | Whether the contractor's programme is realistic and meets the client's dates |
Why do exclusions and qualifications matter so much?
Because they move cost and risk back to the client without showing up in the price. A tender that excludes, for example, dealing with contaminated ground, or assumes the client will provide certain services connections, may be cheaper on paper only because it has left out something another contractor priced. Each exclusion needs a value put against it so that bids can be compared fairly.
Qualifications can be even harder to spot. A line saying the price assumes a particular ground condition, or depends on a specific product being available, can turn into a significant claim later.
What about unusually low bids?
A bid well below the others is worth celebrating only after it has been checked. It may reflect a genuinely efficient contractor. It may also reflect a mistake, a misunderstanding of the scope, or a plan to recover margin through claims. Clarifying the low bid with the contractor, and checking that they will stand by their price, protects both sides.
Is price the only thing to compare?
Rarely. Most clients weigh quality alongside price: the contractor's team, their approach to the project, their programme, their health and safety record and their experience of similar work. Setting the price and quality weighting before tenders are returned, and scoring against it consistently, keeps the process fair and defensible, which matters particularly for public sector clients.
What should the tender report contain?
- A summary of the bids received and any late or non-compliant returns
- The adjusted comparison, showing how each price was normalised
- The quality assessment, if used
- Key risks, exclusions and qualifications for the preferred bid
- Clarifications requested and the answers received
- A clear recommendation, and any conditions attached to it
The report gives the client the basis for a confident decision and a record of why the contractor was chosen.