Cost to complete is the total amount of money still needed to finish a development from where it stands today. A monitoring surveyor works it out by taking the current forecast final cost and subtracting what has already been spent, then testing whether the remaining loan facility and the developer's equity are enough to cover it. If they are not, the scheme has a funding gap, and the lender will want to know how it will be closed.
It is one of the most important figures in development finance reporting, because it links the physical progress on site to the money left in the facility.
How is cost to complete calculated?
| Element | What it includes |
|---|---|
| Forecast final construction cost | Contract sum plus agreed and likely changes, and remaining risks |
| Less: certified to date | Construction work already valued and paid |
| Plus: other costs to come | Professional fees, statutory charges, utilities, warranties, insurances |
| Plus: remaining contingency | An allowance for risks not yet realised |
| Equals: cost to complete | What is still needed to finish |
The surveyor then compares cost to complete with the undrawn loan facility plus any committed equity still to go in. If the funds available are less than the cost to complete, there is a shortfall.
Why is the forecast final cost so important?
Because cost to complete is only as good as the forecast behind it. If the forecast ignores changes the developer has instructed, claims the contractor has submitted, or risks that everyone on site knows about, cost to complete will look better than it really is. Monitoring surveyors look beyond the contractor's application to the change register, correspondence and site conditions to form their own view.
What makes cost to complete move?
- Variations instructed by the developer
- Contractor claims for delay or disruption
- Provisional sums spent above their allowance
- Unforeseen ground or existing building conditions
- Delays that increase fees and finance costs
- Changes to statutory requirements or approvals
Some of these add construction cost directly. Others, such as delay, add cost elsewhere, particularly interest, which is why a slipping programme is a funding issue as well as a construction one.
What happens if there is a shortfall?
The lender will usually expect the developer to fund it, typically by putting in more equity before further drawdowns are released. The facility agreement normally sets out what happens. The earlier a shortfall is identified, the more options there are: value engineering remaining packages, agreeing savings with the contractor or arranging additional funding in good time. Found late, it can stall the project.
How can developers keep it under control?
Run an honest cost report every month, including known risks, and share it openly with the lender's surveyor. Control change carefully. Keep contingency for genuine risks. And raise problems early. Monitoring surveyors are far more comfortable reporting a known issue with a plan to deal with it than discovering one themselves.