All insights Monitoring

The Initial Report: How a Monitoring Surveyor Assesses a Scheme Before Funding

The Initial Report: How a Monitoring Surveyor Assesses a Scheme Before Funding

A monitoring surveyor's initial report, sometimes called a pre-funding or day one report, is the lender's independent review of a development before any money is released. It tests whether the budget is realistic, the programme achievable, the contract suitable, the approvals in place and the team capable of delivering. A well prepared developer can make this stage quick. A poorly prepared one can delay the whole scheme.

Lenders appoint monitoring surveyors because they are funding a building that does not yet exist. The initial report is their first look at whether the scheme stacks up from a construction point of view, separate from the valuation.

What does the initial report look at?

AreaWhat the surveyor checks
BudgetConstruction cost against the design and market rates, fees, contingency, and what is and is not included
ProgrammeWhether the timescale is realistic for the scope and procurement route
ContractThe building contract, amendments, the contractor's risk and the lender's protection
ContractorFinancial standing, track record and capability for this size and type of scheme
DesignHow developed it is, and where design risk sits
ApprovalsPlanning, conditions, building control, and any other consents
Legal and technicalWarranties, collateral warranties, insurances, site investigation, party wall and rights of light matters
Cash flowThe drawdown forecast against the programme

Why does the budget get so much attention?

Because it is the figure the loan is built around. The surveyor wants to see that the cost plan matches the design and specification the scheme is being valued on, that there is a sensible contingency, and that costs such as fees, statutory charges, utilities and professional team appointments have not been left out. A budget that only covers the building contract is a common gap.

They will also compare the contract sum with the cost plan, and look closely at provisional sums and exclusions, since these are where cost growth usually comes from.

What are the usual red flags?

  • A contract not yet signed, or heavily qualified tenders
  • Planning conditions that must be discharged before starting, with no plan to do so
  • Little or no contingency
  • A programme that ignores long lead items or the approvals timetable
  • A contractor whose accounts or recent projects raise questions
  • No site investigation, on a site where ground conditions are a real risk

None of these automatically stops funding. They do usually lead to conditions, extra security or delay while they are resolved.

How can a developer prepare?

Pull the information together before the lender's surveyor asks for it. That means the cost plan and contract, the programme, planning permission and conditions, building control status, design drawings and specification, site investigation, the professional team's appointments and insurances, and the contractor's details. A clear, organised pack lets the surveyor get on with the review rather than chasing documents.

It also helps to be candid about risks you already know about. Monitoring surveyors see a lot of schemes. A known issue with a plan to manage it is far easier to report on than one they discover for themselves.

What happens after the initial report?

Once funding is in place, the surveyor visits the site regularly, usually monthly, and reports to the lender before each drawdown on progress, quality, cost and programme. The initial report sets the baseline those later reports are measured against, which is another reason to get it right.

Spring & Co provides fund monitoring and due diligence for lenders and investors, and project monitoring on developments across the UK. We also help developers prepare for lender scrutiny. Get in touch if you have a scheme heading towards funding.