Reading a Construction Programme: A Client's Guide

Reading a Construction Programme: A Client's Guide

A construction programme is a timeline of every activity needed to complete the project, showing when each starts and finishes and how they depend on one another. The most important thing for a client to find on it is the critical path: the chain of activities that directly decides the completion date. If anything on that path slips, completion slips too.

Most programmes are presented as Gantt charts: a list of activities down the left and horizontal bars across a timeline. They can look intimidating, especially when they run to hundreds of lines. But a client only needs to understand a handful of things to read one usefully.

What are the key parts of a programme?

TermWhat it means
ActivityA piece of work with a duration, such as groundworks or first fix electrics
DependencyA link showing one activity cannot start or finish until another does
Critical pathThe longest chain of dependent activities, which sets the completion date
FloatHow much an activity can slip before it affects the completion date
MilestoneA key date, such as frame complete or building watertight
BaselineThe original agreed programme, against which progress is measured

Why does the critical path matter so much?

Because it tells you where to pay attention. An activity with weeks of float can run late without harming completion. An activity on the critical path cannot. When a contractor reports that something is behind, the first question is whether it is critical. If it is, the next question is what is being done to recover it.

A well built programme shows the critical path clearly, often highlighted in red. If yours does not, ask for it.

What should a client look for?

  • Realistic durations. Compare key activities with similar projects, and ask about anything that looks optimistic.
  • Client dependencies. Activities that need a client decision or input, such as approving finishes or providing access. These are easy to miss and often on the critical path.
  • Long lead items. Plant, lifts, specialist glazing and anything with a long manufacturing time.
  • Statutory approvals. Discharging planning conditions, building control stages and utility connections.
  • Weather sensitive work. Groundworks, roofing and external works timed for winter need allowances.
  • Commissioning and handover. These are often squeezed. They should have realistic time before completion.

How should progress be reported?

Against the baseline. Each month the contractor should show actual progress against what was planned, identify any delay to critical activities, and explain the recovery plan. A programme that is reissued every month with new dates and no reference to the original makes it very hard to see what has really happened.

Under NEC contracts the programme has a formal status and must be submitted and accepted. Under JCT it is less formal, but it is still essential evidence if there is ever a dispute about delay and extensions of time.

What if the programme is slipping?

Ask three questions. What caused it? Is it on the critical path? What is the realistic recovery plan, and what does it cost? Sometimes acceleration is worth paying for, for example where a fixed opening date matters more than the extra cost. Sometimes it is better to accept a later date. Either way, the decision should be made with clear information, and early.