Dilapidations are the repairs, reinstatement and redecoration a tenant was obliged to carry out under a commercial lease but did not. At lease end, the landlord can serve a schedule of dilapidations and claim for them. The claim is limited by law to the loss the landlord actually suffers, and the process is set out in a pre-action protocol. Understanding both early saves landlords and tenants a great deal of money and argument.
Dilapidations disputes are common because they arrive at the worst moment: the tenant is leaving and wants to close the account, and the landlord is facing a building that may need work before it can be relet.
What does the tenant have to do?
That depends entirely on the lease. Typical obligations include:
- Repair. Keeping the premises in repair, sometimes to a higher standard than their condition at the start.
- Reinstatement. Removing alterations the tenant made, if the lease or a licence requires it.
- Redecoration. Decorating in the final year of the term, often to a specified standard.
- Statutory compliance. Meeting legal requirements affecting the premises during the lease.
A schedule of condition agreed at the start of the lease can limit the repair obligation to the condition at that time. Tenants who took on space without one often find themselves liable for older defects.
How does the claim work?
The Dilapidations Protocol, a pre-action protocol for claims about the physical state of commercial property at the end of a tenancy, sets out how parties should behave before any court claim. In outline:
| Step | What happens |
|---|---|
| Schedule | The landlord serves a schedule listing breaches, the work needed to remedy them and its cost |
| Quantified demand | The landlord sets out the sum claimed, with a surveyor's endorsement that it is reasonable |
| Response | The tenant responds item by item, usually with its own surveyor |
| Negotiation | The parties meet and try to settle, and consider other ways of resolving it before going to court |
The protocol expects claims to be realistic and evidenced. Inflated schedules tend to damage the credibility of the landlord's whole case.
What limits the claim?
Section 18(1) of the Landlord and Tenant Act 1927 caps damages for breach of a repairing covenant at the amount by which the value of the landlord's interest has been reduced. So if the landlord plans to redevelop or substantially alter the building, repairs that would be swept away anyway may be worth little or nothing in damages. The same section also means no damages are recoverable for failing to repair if the premises are to be demolished or altered in a way that would make the repairs valueless.
This is why a dilapidations claim is never simply the cost of the work. The landlord's plans for the building matter a great deal.
What should tenants do?
Start early, ideally a year or more before the lease ends. Read the lease and any licences, commission a surveyor's review of likely liabilities, and decide whether to carry out the work or negotiate a cash settlement. Doing the work yourself can be cheaper than paying the landlord's estimated cost, but it has to be done to the standard the lease requires.
What should landlords do?
Serve the schedule in good time, keep it to genuine breaches, price it realistically and think about the section 18 cap before issuing a demand. If you plan to refurbish, be honest about it, because it will come out in negotiation.
How we help
Our property consultancy team advises landlords and tenants on dilapidations, schedules of condition and lease end negotiations, and our tenant management service helps landlords keep on top of repair obligations during the lease. Talk to Spring & Co about a lease coming to an end.