Practical completion is the point at which the works are complete for practical purposes and the building can be handed over. It matters because of what it triggers: under most contracts it releases half of the retention, starts the rectification period, ends the contractor's exposure to delay damages and passes responsibility for the building, including insurance, to the client. Once it is certified, much of your bargaining power has gone, so check before you accept.
JCT contracts do not define practical completion precisely, and there has been plenty of argument about what it means over the years. In general terms, the building should be complete apart from very minor items, and capable of being used for its intended purpose.
What should be finished before practical completion?
At a minimum:
- All construction work complete, apart from minor snagging that does not affect use
- Building services installed, commissioned and working
- Fire safety systems tested and certified
- Building control completion certificate obtained, or clearly on its way
- Health and safety file and operation and maintenance information provided, or agreed to follow promptly
- Keys, access controls and warranties handed over
Many contracts and employer's requirements set out their own conditions for practical completion, such as specific documents or tests. Read them early, not in the final week.
What is the difference between snagging and incomplete work?
Snagging covers minor defects and finishing issues that do not stop the building being used: a scuffed door, a missing sealant bead, a light fitting slightly out of line. Incomplete work is work that has not been done. A building with an unfinished fire alarm installation is not practically complete, however small the list looks.
The distinction matters because some contractors push for practical completion with a long list of "snags" that are really outstanding work. Accepting that shifts cost and risk to the client.
| Area | What to check |
|---|---|
| Fabric | Finishes, doors, windows, roof, external works complete |
| Services | Commissioning certificates, witnessed tests, controls set up |
| Fire safety | Alarm, emergency lighting, fire stopping records, door certification |
| Compliance | Building control, energy certificates, any planning conditions |
| Information | O and M manuals, as-built drawings, health and safety file |
| Handover | Keys, training for your facilities team, warranties |
Who inspects before practical completion?
Usually the contract administrator or employer's agent, supported by the design team and the client's quality inspector if there is one. The inspection should be planned, with a clear checklist, and it should happen before the contractor applies for practical completion rather than on the day. Pre-completion inspections give the contractor a fair chance to finish properly and avoid last minute arguments.
What if the building is needed before everything is done?
It happens, especially where a client has a fixed opening date. The options include partial possession of finished parts, sectional completion if the contract allows it, or agreeing early access for fit out under clear terms. What should be avoided is certifying practical completion for a building that is not complete, simply because the date has arrived. The consequences run on well beyond handover day.
What happens next?
The rectification period begins. Defects that appear are notified to the contractor, who returns to fix them. At the end of the period, a final schedule of defects is issued, and once those are made good, the rest of the retention is released and the final account can be settled.
A well managed practical completion makes all of that straightforward. Our quality assistance and project supervision teams inspect, record and manage completion on behalf of clients, under our ISO 9001 quality system. Talk to Spring & Co before your next handover.