The defects period, called the rectification period in JCT contracts and the defects date period in NEC, runs from practical completion, commonly for twelve months. During it the contractor must return and put right defects that appear. Used well, it is the client's best chance to find and fix problems at the contractor's cost. Used badly, it ends with a rushed inspection and a building that still has problems.

Many clients treat the months after handover as the end of the project. In reality, a new building's first year is when most latent defects show up: leaks after the first heavy rain, heating that struggles in the first winter, cracks as materials dry out and the structure settles.

What counts as a defect?

Work or materials that do not comply with the contract. That includes things that are wrong from the start and things that fail because they were not installed properly. It does not usually include damage caused by the occupier, normal wear and tear, or changes the client made after handover.

How should defects be recorded?

Consistently, in one place, from day one. A simple defects log, shared with the contractor, should record:

  • What the defect is and where it is
  • The date it was found and reported
  • A photograph
  • Whether it is urgent, for example a leak or a safety issue
  • When it was fixed and who confirmed it

Urgent defects should be reported to the contractor straight away. Others can be batched and reported regularly. Most contracts allow the client to notify defects during the period and require a final schedule at the end.

WhenWhat to do
At handoverConfirm outstanding snags and start the defects log
First monthCheck services settings, controls and alarms under real use
First winter and heavy rainCheck roofs, gutters, windows, heating performance
ThroughoutLog defects as found, report urgent ones immediately
Before the period endsFull inspection and final schedule of defects

Why is the end-of-period inspection so important?

Because the final schedule of defects is usually the client's last chance under the contract to have the contractor put things right at their own cost before the remaining retention is released. After that, remedies are still possible but are slower, more expensive and more adversarial. A thorough inspection, planned a month or two before the period ends, is well worth the effort.

The inspection should cover the whole building, including roofs, plant rooms and external works, and it should draw on feedback from the people who use the building every day. They often know about problems nobody has formally reported.

What if the contractor does not return?

Most contracts allow the client to use the retention to pay another contractor to put right defects the original contractor fails to fix, after following the notice process. That is one of the main reasons retention exists. It is a last resort, though. A well managed defects process with clear records usually keeps the contractor engaged.

Who should manage it?

Someone with time and technical knowledge. That may be the client's facilities team, the project manager or an independent quality inspector. What matters is that it is someone's job, not an afterthought.

Our quality assistance team manages defects periods and end of period inspections for clients, and our tenant management service supports landlords with occupiers during the first year. Talk to Spring & Co about the months after your next handover.